Fortec was engaged by Delta Corp to carry out the supply, installation, stressing and testing of 16 No 1000kN WL active permanent hold down anchors.
The permanent anchors were required to hold down 92m long prestressing bed for major bridge precast girder forms.
Fortec works were completed along the surface of the bridge girder concrete tub/form with Fortec’s specialist tight access plant and equipment without disruption to precast production schedules and maintained a safe and functional work environment.